FUTURE FACILITY

The greatest investment of our lives, outside of our own family, is in the local church.

Current Timeline (as of 9/4/22):

What We've Done So Far:

  • November 2019 | $252,000 was committed for 24 months by 35 families 
  • May 2020 | Purchased 2.45 acre parcel for $220,000 (assessed at $320,700)
  • October 2020 | Site Plan submitted to Stafford County
  • November 2020 | Conditional Use Permit (CUP) submitted to Stafford County
  • December 2020 | Steel order placed for October 28, 2021 arrival
  • December 2020 | Building Plan submitted to Stafford County
  • January 2021 | $150,000 investment to help with purchase of steel or paying off land
  • February-November 2021 | Lending and permitting secured to begin site work/construction
  • February 24: First Public Hearing - Passed
  • April 20: Second Public Hearing - Passed
  • July 19: Third Public Hearing - Passed
  • October 22: Received State Approval
  • October 28: Steel Delivered
  • December 3: Final Approval


What's Next:

  • December 8, 2021 | Construction Started
  • January - March | Erosion Control; Grading
  • April | Footings; Foundation; Rough Plumbing; Rough Electrical; Slab
  • May | Steel Erection
  • June - October | Site Work; Electrical; Plumbing; Gas; Drywall; AVL; Cabinetry; Flooring; Landscaping; Paving
  • November 2022 | Move-in 


Next Steps:

  • Our church will have opportunities for special gatherings at the property
  • Our church will also be working on the facility (flooring, landscaping, AVL, furnishings) in the fall