BUILDING PLANS

The greatest investment of our lives, outside of our own family, is in the local church.

Current and Projected Timeline (as of 6/4/21):

What We've Done So Far:

  • November 2019 | $259,300 was committed for 24 months by 37 families 
  • May 2020 | Purchased 2.45 acre parcel for $220,000 (assessed at $320,000)
  • October 2020 | Site Plan submitted to Stafford County
  • November 2020 | Conditional Use Permit (CUP) submitted to Stafford County
  • December 2020 | Steel order placed for May 28, 2021 arrival
  • December 2020 | Building Plan submitted to Stafford County
  • January 2021 | $150,000 investment to help with site work or paying off land


What's Next:

  • January-June 2021 | Lending and permitting secured to begin site work/construction
  • February 24: First Public Hearing - Passed
  • April 20: Second Public Hearing - Passed
  • June 28: Closing on Construction Loan
  • July 19: Third Public Hearing
  • August 28: Steel Delivery
  • August 2021 | Construction Begins
  • March 2022 | Move-in 


Current Pre-Construction Costs:

  • Feasibility Study | $7,960.50 of $7,960.50
  • Land Purchase | $5,053.75 of $220,000.00 
  • Architectural Fees | $76,053.86 of $97,000.00
  • Civil Engineering and Site Work Fees | $43,237.47 of $54,642.70
  • Stafford County Fees | $24,035.17 of $64,035.00
  • FF&E | $56,377.00 of $137,000.00
  • Construction Loan Closing Costs | TBD
  • Steel | $209,014.37 of $209,014.37
  • Total Paid | $412,933.81 of $789,652.57 (52%)


Capital Campaign Commitments:

  • 48 Commitments (+11 since start of the campaign)
  • Total Given | $222,284.61 of $263,200.61 (84%) 


Next Steps:

  • Receive permitting. This allows us the right to move dirt and build.
  • Lending secured. Closing is projected for June 28, 2021 on construction loan. Our attorney is reviewing the loan documentation.