Current Timeline (as of 4/22/22):
What We've Done So Far:
- November 2019 | $252,000 was committed for 24 months by 35 families
- May 2020 | Purchased 2.45 acre parcel for $220,000 (assessed at $320,700)
- October 2020 | Site Plan submitted to Stafford County
- November 2020 | Conditional Use Permit (CUP) submitted to Stafford County
- December 2020 | Steel order placed for October 28, 2021 arrival
- December 2020 | Building Plan submitted to Stafford County
- January 2021 | $150,000 investment to help with purchase of steel or paying off land
- February-November 2021 | Lending and permitting secured to begin site work/construction
- February 24: First Public Hearing - Passed
- April 20: Second Public Hearing - Passed
- July 19: Third Public Hearing - Passed
- October 22: Received State Approval
- October 28: Steel Delivered
- December 3: Final Approval
What's Next:
- December 8, 2021 | Construction Started
- January - March | Erosion Control; Grading
- April | Footings; Foundation; Rough Plumbing; Rough Electrical; Slab
- May | Steel Erection
- June - August | Site Work; Electrical; Plumbing; Gas; Drywall; AVL; Cabinetry; Flooring; Landscaping; Paving
- September 1, 2022 | Estimated Move-in
Next Steps:
- Our church will have opportunities for special gatherings at the property
- Our church will also be working on the facility (flooring, landscaping, AVL, furnishings) in the summer